| |
Click
here to jump to progress pictures from summer and fall 2006.
April 13, 2006 Chris Kuehnel did a brief walk through with Rolf, of the
Johnson Barn just north of Cleveland. We found and identified significant
damage from moisture at the perimeter, failing foundation elements, and animal
and tree damage. The standing seam metal roof is in very good condition
and the barn is repairable over a three to six year timeframe. Without
immediate prioritized attention as detailed, it can be expected that this
structure will fail during the next 12 months.
Click on any pic to see full view, then
use back arrow to return here....... |
|
|
|
|
|
A |
B |
C |
D |
E |
In our view this would be the best sequence of work:
By June 1, 2006:
- 1) have a gutter installed on the north roof to keep moisture away from
the building. Anticipated cost $750 by contractor. See Pic A.
- 2) remove the two large trees on the barn hill and west of the hill, and
trim back all branches on all other trees within ten foot of the building.
For the cedars in the corners of the shed, trim all branches within two feet
of the building. Owner to do the work, or we can do it for $750 total.
Owner to maintain trees each year.
- 3) Owner to cleanup barn hay mow floor so all can be accessed and made
safe.
By July 1, 2006
- 4) install vertical temporary braces in the barn basement.
One in the NE corner, one next to the stairs, one to replace the missing one
near the SW corner, and a row of posts across the approximately 35' of south
wall and 3 to 5 foot in from south wall, to be installed at a 2-5 degree
angle back to the north to oppose the tendency for the floor joists and
girders to slide south as it has been doing. Lift and support south
center main posts to align plate and wind braces in hay mow. Design
for two to three year life. Cost: $1000-1500. Pics B,C,D
- 5) build and install two large barn doors for the north and south sides
to replace those which have been removed. Cost $1500. See Pic A.
- 6) Owner to remove burrowing animals that are undermining foundation in
several locations.
- 7) Cover failed barn floor boards with planking or OSB 'chipboard'.
Cost: $350.
- 8) Stabilize brick infill in north building. Cost $50, See
pic E.
By July 1, 2007
- 9) owner to remove the old hay/straw in the west mow
- 10) repair the west wall with technique to be determined at that time.
Anticipated cost: $2000+.
- 11) replace failed barn floor boards Cost: $500 less recovery of
any usable OSB from 2006.
By July 1, 2008
- 12) repair/replace the south portion of the lower wall.
Anticipated cost: $2500 if foundation is usable. Pic C.
- 13) do minor repair and stabilization as needed on the north and south
sheds.
We are able and interested in doing all work except for the hanging of
gutters. Can do the barn door construction or you can let that to another
contractor.
All costs are approximate and are presented here solely for planning
purposes. Building condition and thus costs to repair more than three
months in the future are not predictable and will need to be re-quoted before
that portion of the repairs is to be done.
Chris Kuehnel
Elemental Services
920-693-3141
cqnel@clevelandwi.net
Phase 1 Progress
and Completion Pictures (scroll right or left and view medium pic below).
Priority repair completed, north side tie beam above main door had a major failure in the tenon, pulled it back together, secured for another 50 years
|